Review Jakarta LRT Project, Trackwork Progress Reaches 95

Jakarta LRT Progress

Review Jakarta LRT Project, Trackwork Progress Reaches 95%

As of January 2019, the work of the Trackwork on the Kelapa Gading - Velodrome Jakarta Light Rail Transit (LRT) Construction Project has reached 95 percent progress.

The entire Jakarta LRT Trackwork work is handled by WIKA Beton-Emrail KSO and this work is divided into two areas, namely Mainline and Depo Pegangsaan Dua (ground floor & 1st floor).

Review Jakarta LRT Project, Trackwork Progress Reaches 95 Percent

On the Mainline area, construction work has been completed 100%. Meanwhile, in the area of ​​Pegangsaan Dua Depo both on the ground floor and on the 1st floor, construction work is still continuing along with the Jakarta LRT Main Cross Supporting Facility Test that connects the Velodrome Depo Pegangsaan Dua. This activity indicates that the Trackwork work process is about to complete.

In this LRT Trackwork work, the WIKA Beton-Emrail KSO contribution includes Engineering, Procurement and Construction. In the future, WIKA Beton would target similar projects, particularly in Trackwork project.